Weeks 40-41: Getting it Liveable

The time has come when our budget and timescale has dictated that we need to move in to the house – so the past couple of weeks have been a huge push from our builders to get the place liveable and safe so that we can stay there.

IMG_7486

First up was getting running hot water through the house. The boiler had been installed but none of the bathroom fittings had been finished, nor the radiators in so this was a key job to be done.

Like our splash-back decision? It’s a copper metallic effect on glass. I especially love the way it reflects the crap that’s currently being stored in the utility room!

The bathrooms were all (and still are!) at different stages of completion, so the team worked on having at least one complete bathroom and another running toilet.

The first one to be finished with fittings, running water and lighting was the loft en-suite:

DSC02877

IMG_1504

IMG_1476

So nice to have running water. All that’s left in this room is the PIR automatic light and the splash back.

The other bathrooms are shaping up nicely too!

Here is the small loft bathroom:

 

The front bathroom:

(check out the shutters!)

Family Bathroom:

Woohoo we have a bath!

DSC02871

Still a few lighting bits and fixings to go but they are nearly there.

Next was getting electricity running and putting faceplates on so we can plug things in! We prioritised the rooms that had carpet in and shutters so that we would be able to have a decent night sleep. We now have two rooms that have carpet, shutters and lighting in:

Side bedroom:

DSC02873

Rear loft room:

DSC02876

Plus the loft master bedroom is also carpeted but no shutters yet:

DSC02879

Here’s a fittings montage:

This still means we don’t have lighting downstairs bit at least it is summer! The ovens, fridges and tap works and after a clearcut and a clean the kitchen looks like this:

DSC02867

DSC02864

DSC02866

DSC02862

We are especially pleased with our fancy hob, which is not only induction, but has an extractor built in which meant we didn’t need to have a bulkhead above the island.

DSC02868

It is from German brand, Bora and was sourced by our kitchen suppliers.

Also – cue fanfare – the scaffolding has been taken down after 9 months and the new restored brickwork can be revealed!!!

DSC02881

I can’t stop looking at it. what a transformation from how it was before:

IMG_0152

Now that we are in, it is actually really beneficial being in it every morning and evening. We still don’t have any furniture, and living in the space really helps to make decisions. Hoping that we can soon so that we can start booking friends and family round to stay when it is more finished!

K

 

Week 39: Second Fix is Underway

It’s been an exciting week over at the house as many of the fittings have started getting fixed in, making it look a lot more like a house and less like a building site.

In the two reception rooms we’ve had the oak flooring laid. We chose a chevron design and the pieces have a large variation in colour and grain which makes it look different from each angle you enter the rooms.

DSC02783

I also think it is going to make these rooms look huge. I’d read that chevron apparently does this more so than herringbone. In fact we were OK with either, it just so happened that there was the right amount of stock in this pattern on the Havwoods Clearance website!

IMG_1408

Upstairs the bathrooms are beginning to look more finished as the sinks, vanity units and toilets have been put in to place

IMG_1421

Loft rear bathroom

This is the smallest of our four bathrooms and was an odd layout to get right because of the head height restriction near the toilet – but thankfully each item is in good proportion.

IMG_1416

Double sink in the front bathroom

You’ll remember from a previous post that we added a bathroom in the front of the house and were debating over whether to have a double sink or a bath. I’m pleased we went for a double sink. Plus we got a clever cabinet that is hidden in to the stud wall which makes it flush to the bathroom wall and looks awesome.

IMG_1417

The sink is matt, which is the same as the shower tiling and the bath in our family bathroom. This unit is in a concrete grey effect, which goes well with the marble effect porcelain tiles. All bathroom fixings are from CP Hart, some from the main shop and some from their outlet centres.

IMG_7202

Sink in loft en-suite

In two of the bathrooms we went for the same style sink with a thicker shelf on one side. These are great for those bathrooms that have limited storage space like our loft that has a sloping ceiling so we couldn’t get a cabinet in. It does mean the tap is off-centre though.

The bedrooms have all been painted and skirting down ready for the carpet that comes next week! We also picked a lovely decorative fireplace for the front bedroom (the one with a bay window) This is from a local fireplace restoration place.

K